West Linda Comprehensive Safe Routes to School Project

The West Linda Comprehensive Safe Routes to School Project aims to significantly improve pedestrian and cyclist safety by redesigning and enhancing the infrastructure around key educational facilities.

Resident Action Needed

In order for construction to move forward, property owners are encouraged to complete the Permit to Enter form. This form grants the County access to complete work such as driveway conforms, drainage improvements, and relocating fence and other miscellaneous items as necessary to build the new roadway and storm drain system.

Join Us in Planning Exciting Changes for the West Linda Community

In 2023, Yuba County was awarded a $21 million grant from California's Active Transportation Program to fund the West Linda Comprehensive Safe Routes to School Project. This project will enhance pedestrian connections and improve safety around local schools by constructing sidewalks, crosswalks, accessible ramps, bicycle lanes, and curbs.

In addition to sidewalks and bike lanes, the project includes the installation of storm drains and gutters to address standing water issues and reduce flood risk.

The West Linda Comprehensive Safe Routes to School Project will improve transportation and access within West Linda to make our community safer and more connected than ever before – improving how residents get around, whether it's walking, biking, or driving, and creating safer paths to schools and other key destinations.

Map of roads involved in west linda safe routes to school project and cedar lane elementary and new life christian school

Timeline

December 2024

Design reached 65% milestone

December 2024

July 2025

Design plans & specifications at 95%

July 2025

November 2025

Design plans & specifications at 100%

November 2025

March 2026

Construction Bid Advertisement

March 2026

April 2026

Construction Bid Opening

April 2026

June 2026

Construction Contract Award

June 2026

July 2026

Break Ground

July 2026

Frequently Asked Questions

General Project Overview

Design, Construction, and Timing

Project Benefits and Community Impact

Resident Impact and Accessibility

About the West Linda Safe Routes to School Project

Project Benefits Include:

  • Enhanced safety and accessibility for students walking or biking to school, particularly those attending Cedar Lane Elementary and New Life Christian School
  • Improved drainage infrastructure to prevent flooding and enhance community resilience
  • Use eco-friendly techniques to repair roads, making them last longer and causing less harm to the environment
  • Strengthened community connections with safer access to local destinations and amenities

Key Elements:

  • Community Connectivity: Enhancing access to schools, parks, businesses, and community amenities, the project fosters safer and more convenient pathways for all residents, promoting a vibrant and connected West Linda community.
  • Stormwater Drainage: Addressing existing flooding issues, the project includes designing a drainage system that aligns with the County's vision of a multi-use West Linda Drainage Basin. This system will manage runoff effectively and enhance community resilience.
  • Utilities: The project involves coordinating the relocation of overhead poles, fire hydrants, sewer manholes, and water meters to accommodate the safe routes.
  • Pavement Improvements: The project evaluates street improvement options, considering cost-effectiveness and sustainability.